Which technique will help the project manager to accelerate the deliverable?

After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.

Which technique will help the project manager to accelerate the deliverable?
A . Impact mapping
B. Rolling wave planning
C. Collective code ownership
D. Scrum of Scrums

Answer: B