What should the project manager have done to prevent this from happening?

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval.

What should the project manager have done to prevent this from happening?
A . Sent the meeting minutes to the stakeholders after the kick-off meeting
B. Reviewed all the approvals immediately after the kick-off meeting was over
C. Ran separate kick-off meetings for each culture and time zone
D. Validated each stakeholder’s understanding during the kick-off meeting

Answer: D