Which activity should be considered as a priority?

A research and development team is finishing up a two year initiative. The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?
A . Mark the product backlog completion status and update the communications management plan.
B. Ensure that knowledge transfer activities are executed as planned
C. Release the resources and plan for a project completion celebration.
D. Hold a steering committee meeting to inform them of the project completion

Answer: B