What should the project manager do to reduce negative impacts to the project?

The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication. The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project

What should the project manager do to reduce negative impacts to the project?
A . Modify the communications management plan to account for regional differences
B. Conduct cultural awareness seminars
C. Hold a virtual meeting to discuss the political environment.
D. Conduct a multigenerational management training session

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments