At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?

From previous lessons learned working with a client, a project manager notes that the client’s turn-around times on documents sent for approval were very slow and well outside of the agreed timelines.

At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
A . Inform the client that extra resources will be added to give the client more time for reviews.
B. Update the project risk register with the potential for delays
C. • Work with the client on an acceptable amount of time for document approval
D. Inform the client of their responsibility in relation to document approval

Answer: C