What should the project manager do?

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?
A . Delay the project until the issue is addressed and no longer presents as a risk to the project.
B. Inform the sponsor that the issue has arisen and that the project’s success may be uncertain
C. Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.
D. Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Answer: D