What factor should the project manager consider when determining if the project is suitable for an agile approach?

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach.

What factor should the project manager consider when determining if the project is suitable for an agile approach?
A . The project is an information technology project and has minimal impact to the organization
B. The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).
C. The project scope is well defined and the requirements are prioritized
D. The project team has a colocated space and is capable of working together

Answer: D