What does the project manager need to do first in order to have good project performance?

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches.

What does the project manager need to do first in order to have good project performance?
A . Coach those team members lacking hybrid knowledge to learn on the job.
B. Change the team to include hybrid experts
C. Assess the required training per team member.
D. Deliver hybrid training to all team members

Answer: C

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments