When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain.

When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?
A . Probability assessments
B. Collaborative discussions
C. Workshops for risk avoidance
D. Interview with the project champion

Answer: B