The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members’ performance. The project manager wants to understand the situation and provide feedback to the team as soon as possible

What three actions should the project manager take to address this situation? (Choose three)
A . Define team ground rules
B. Perform a retrospective session
C. Implement daily team meetings.
D. Request a manager performance review
E. Conduct an annual review.

Answer: A,B,C