What should the project lead do next?

A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months.

What should the project lead do next?
A . Schedule meetings with the customer to determine their ability to support multiple incremental deliveries
B. Work with the agile team to schedule the incremental deliveries to enable delivery of business value sooner to the customer.
C. Work with the stakeholder to understand what the concerns are while at the same time conveying the benefits of incremental deliveries
D. Provide details of the concern to the agile team and adjust their goals and release plans to conform to the stakeholder’s request.

Answer: C