What should the project manager do to enhance project team effectiveness?

A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages. This difficulty leads to missed deadlines.

What should the project manager do to enhance project team effectiveness?
A . Implement team colocation to improve communication.
B. Identify the root cause of communication issues
C. Initiate daily communication of project progress
D. Schedule a communications control board meeting

Answer: B