How should the project manager respond?

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation.

How should the project manager respond?
A . Tell the junior team member that the information is available in lessons learned
B. Offer guidance and follow up with some developmental activity for the junior team member
C. Inform the junior team member that risk mitigation is not part of their work
D. Refer the junior team member to the senior team member who develops the risk mitigation strategy

Answer: B