Which team is performing better?
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points
Which team is performing better?
A . Team A as they have calculated fewer story points than team B.
B. Team B as they have calculated more story points than team A
C. The team that completes the most stories selected from the sprint backlog
D. The team with the least amount of defects in their deliverables
Answer: D