Which project approach suits the scenario?

A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year

Which project approach suits the scenario?
A . Execute it as a Scrum project
B. Execute it as a predictive project
C. Execute it using the same approach as the reference project
D. Execute it as a project with stage gates

Answer: A