What should the project manager do?

During the review of a project’s list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed .

What should the project manager do?
A . Check the approved list of requirements to see if there are any missing items.
B. Work with the stakeholder to improve the requirements’ acceptance criteria
C. Review the requirements traceability matrix with the concerned stakeholder
D. Discuss with the stakeholder which additional requirements should be added

Answer: C

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments