During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?
A . Revisiting the project management plan to ensure deliverables are on time
B. Increasing the frequency of project update meetings to keep stakeholders informed
C. Revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders
D. Reviewing the business case and identifying gaps within scope

Answer: D