What should the project manager do to analyze the involved stakeholders?

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?
A . Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project
B. Use lessons learned from the previous project as a guide for the current project’s stakeholder register
C. Refer to the stakeholder register from the previous project as it was similar to the current project
D. Document in the risk register that the current project may have different stakeholders than the previous project

Answer: B

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments