What should the project manager do?

A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change.

What should the project manager do?
A . Make the decision on behalf of the organization
B. Review the stakeholder map along with the organizational chart and delegate the most senior person to make the decision
C. Schedule a project decision meeting with all stakeholders to discuss the decision.
D. Follow the stakeholder engagement plan

Answer: C