Which two actions should the project manager take initially to resolve this problem?

A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence. The project is ahead of schedule and running under budget

Which two actions should the project manager take initially to resolve this problem? (Choose two)
A . Check the risk register for a prepared response to a resource being suddenly unavailable.
B . Check if the team member’s activities are sufficiently documented to facilitate handover
C . Check the project’s responsibility assignment matrix (RAM) to determine which activities will be affected
D . Reassign responsibilities across the remaining members using the available float for training.
E . Obtain the project sponsors support to replace the team member on leave

Answer: A,C