What should the project manager do?

A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization’s senior management and external stakeholders .

What should the project manager do?
A . Review the stakeholder register and ensure that communications are being followed in line with the communications management plan.
B . Isolate the project team from external factors such as senior management and stakeholders so that decisions can be made more quickly
C . Review the remaining scope and rebaseline the project’s schedule to take into account delays in decision making
D . Review the adequacy of the project’s governance and ensure that an appropriate structure is in place

Answer: A