What does the project manager need to do first in order to have good project performance?

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches.

What does the project manager need to do first in order to have good project performance?
A . Coach those team members lacking hybrid knowledge to learn on the job.
B . Change the team to include hybrid experts
C . Assess the required training per team member.
D . Deliver hybrid training to all team members

Answer: C