What should the project manager do first?

The sponsor is supportive in leveraging agile approaches. The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders

What should the project manager do first?
A . Determine which agile software tools will be required to support agile delivery within the organization
B . Select a current predictive project define the approach, and provide agile training to execute the remainder of the project
C . Start with a pilot project of appropriate complexity and provide agile training to those who are impacted
D . Determine how to transform the organization using agile techniques, including organizational training and communications

Answer: C