During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?
A . Revisiting the project management plan to ensure deliverables are on time
B . Increasing the frequency of project update meetings to keep stakeholders informed
C . Revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders
D . Reviewing the business case and identifying gaps within scope

Answer: D

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments