What should the project manager do?

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team .

What should the project manager do?
A . Ask the team member to enter this potential schedule delay in the risk register.
B . Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges
C . Actively listen to the team member and identify ways to support their needs in completing the tasks.
D . Set up team-building activities with the project team members to reduce tension

Answer: C