What will the project manager need to focus on as a result of this decision?

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track.

What will the project manager need to focus on as a result of this decision?
A . Increased bum rate
B . Increased cost
C . Increased technical debt
D . Decreased efficiency

Answer: C