What should the project manager do?

An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project

What should the project manager do?
A . Train the team on the new regulations as requested by management
B . Get commitment from the team to include all of the required regulations
C . Ask the project sponsor to add more time to the project.
D . Share with participants the need to focus only on product functionality

Answer: B