What should the project manager do next with this opportunity?

During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level

What should the project manager do next with this opportunity?
A . Share this opportunity with another project
B . Establish a contingency reserve to support the opportunity
C . Further monitor the opportunity
D . No more action is required

Answer: B