While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds. The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?
A . Ask the product designer why the deviation was not considered in the design phase
B . Report to the project sponsor that the product is working and the project is struggling with the budget.
C . Evaluate and initiate the change request process with the stakeholders
D . Ask the quality team to discard the sample and test again with a new sample

Answer: C