What should the project manager do first?

A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.

What should the project manager do first?
A . Develop the resource management plan and ensure adequate training
B . Replace the current project team members
C . Outsource the task to be completed by a specialized vendor.
D . Update the issue log to account for the lack of team member qualifications

Answer: A