How should the project manager handle this situation?

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors. The project is ongoing and uses a hybrid approach. The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?
A . Allocate and use part of the project’s contingency reserves for training purposes.
B . Negotiate a contract and form a partnership with a local authority for medical and security support services.
C . Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training
D . Hire only local resources who are aware of the terntory’s hazards, providing employment to the local community

Answer: C