What should the project manager do to realize benefits?

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch

What should the project manager do to realize benefits?
A . Add an entry in the risk log
B . Implement the changes
C . Review target benefits.
D . Improve the team’s velocity

Answer: B