What should the new project manager do to address the process improvements?

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company’s quality management process.

What should the new project manager do to address the process improvements?
A . Understand the context and interdependencies of the process from the team members and then define improvements
B . Continue with the process as is. and wait until the next phase to suggest any improvements
C . Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework
D . Define a ground rule to comply with the quality standard and ask the team members to apply it.

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments