What should the project manager do?

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?
A . Delay the project until the issue is addressed and no longer presents as a risk to the project.
B . Inform the sponsor that the issue has arisen and that the project’s success may be uncertain
C . Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.
D . Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Answer: D

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments