The customer’s project manager changes during the final stage of a project.

The customer’s project manager changes during the final stage of a project.

How can the project manager avoid a project closure delay’
A . Update the stakeholder engagement plan
B . Review the latest project status report and update the stakeholders
C . Escalate the case to the customer’s management team
D . Issue the project payment invoice to the customer in advance

Answer: A