How should the project manager respond?

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation.

How should the project manager respond?
A . Tell the junior team member that the information is available in lessons learned
B . Offer guidance and follow up with some developmental activity for the junior team member
C . Inform the junior team member that risk mitigation is not part of their work
D . Refer the junior team member to the senior team member who develops the risk mitigation strategy

Answer: B

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments