What should the project manager do to analyze the involved stakeholders?

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?
A . Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project
B . Use lessons learned from the previous project as a guide for the current project’s stakeholder register
C . Refer to the stakeholder register from the previous project as it was similar to the current project
D . Document in the risk register that the current project may have different stakeholders than the previous project

Answer: B