Which of the following would be the MOST beneficial?

A project manager is attempting to establish the proper sequencing and duration of project activities.

Which of the following would be the MOST beneficial?
A . Network diagram
B . Ishikawa diagram
C . WBS
D . Gantt chart

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160