Which of the following stages BEST explains this situation?

A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well .

Which of the following stages BEST explains this situation?
A . Norming
B . Performing
C . Forming
D . Storming

Answer: C