Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?

A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call .

Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?
A . Define the communications plan.
B . Record the missed tasks on the issue log.
C . Provide meeting minutes after each call.
D . Complete a fishbone diagram.

Answer: A