- All Exams Instant Download
Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?
A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call .
Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?
A . Define the communications plan.
B . Record the missed tasks on the issue log.
C . Provide meeting minutes after each call.
D . Complete a fishbone diagram.
Answer: A
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments