Which of the following should the project manager do to resolve this issue?

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?A . Update the scope management plan.B . Modify the project baselines.C . Implement change control...

Continue reading

Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?

One deliverable failed during testing, and this has already happened several times. Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?A . Run chartB . Fishbone diagramC . Scatter diagramD . Gantt chart View Answer Answer: B Explanation: Reference: Kim Heldman, CompTIA...