Which of the following activities are associated with the closing phase of a project? (Choose two.)

Which of the following activities are associated with the closing phase of a project? (Choose two.)A . Risk mitigationB . Archiving of project documentsC . Tracking of expendituresD . Lessons learnedE . Quality assurance View Answer Answer: B,D Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 338, 339...

Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?

One deliverable failed during testing, and this has already happened several times. Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?A . Run chartB . Fishbone diagramC . Scatter diagramD . Gantt chart View Answer Answer: B Explanation: References: Kim Heldman, CompTIA...