Which of the following steps should take place NEXT?

A customer has requested additional features for an active project.

Which of the following steps should take place NEXT?
A . Implement the requested changes.
B . Evaluate the impact of the changes.
C . Update all project documents.
D . Submit the requested changes to the CC

Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293