Which of the following should the project manager do NEXT?

A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule .

Which of the following should the project manager do NEXT?
A . Determine the expected duration of the rework and complete a charge request to modify the project baselines.
B . Notify the project sponsor to schedule and facilitate a team meeting to rework the design documentation.
C . Determine the expected duration of the rework with any associated quality control activities and add the duration to an updated version of the WB
E . Update the master project schedule, and distribute it all stakeholders in accordance with the project communications plan.

Answer: A