Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?
A . SCRUM retrospective
B . Kickoff meeting
C . Budget baseline
D . Risk review

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306