Which of the following is the BEST way for the project manager to address the issue?

A project manager is unsure if the quality of a deliverable from a SME meets specifications.

Which of the following is the BEST way for the project manager to address the issue?
A . Conduct a face-to-face or telephone meeting with the team member.
B . Send an email outlining the concerns to the team member.
C . Send a project team meeting to obtain feedback from everyone.
D . Post the issue on the wiki page for input from stakeholders.

Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261

Latest PK0-004 Dumps Valid Version with 574 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments