Which of the following activities should be done FIRST?

A governance committee has just approved a new project. The project scheduler is now developing the project schedule.

Which of the following activities should be done FIRST?
A . Add durations.
B . Add the start and finish dates
C . Add tasks.
D . Add resources.

Answer: C