Which of the following factors is the MOST likely cause for this scenario?

The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager.

Which of the following factors is the MOST likely cause for this scenario?
A . Personal preference
B . Intra-organizational differences
C . Culture
D . Time zone

Answer: D