While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact.

While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact.

The project manager directs the team to look in the:
A . quality plan.
B . project management plan.
C . risk register.
D . process diagram.

Answer: A

Latest PK0-004 Dumps Valid Version with 574 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments