Which of the following describes how the project manager should BEST determine the initial sequence and durations?

After identifying all known tasks, the project manager has started to sequence and set durations.

Which of the following describes how the project manager should BEST determine the initial sequence and durations?
A . Use milestones identified in the project charter.
B . Use data based on past knowledge.
C . Hold a full team workshop to review the complete WB
E . Collaborate with other project managers.

Answer: A

Latest PK0-004 Dumps Valid Version with 574 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments