Which of the following site types is the PM requesting?

The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project’s success. Only personnel who need to know the information will have access.

Which of the following site types is the PM requesting?
A . Wiki page
B . Intranet
C . Extranet
D . Internet
E . Knowledge base

Answer: A